The state of play with the St James Park redevelopment on Wednesday, July 5.
The Away end:
The terracing has been completely removed to allow access for the redevelopment of the Stagecoach Stand in the near future.
IP Office Main Stand Changing Rooms:
Final preparations are taking place in readiness for the laying of the concrete which takes place this week. Insulation and a protective membrane have also been installed (as pictured below).
Thatchers Big Bank toilets:
The delivery and laying of concrete for the base of the new toilet block took place this week, with the brickwork build also being started.