Redevelopment update: August 16

The state of play with the St James Park redevelopment on Wednesday, August 16.

Now that the new season is well underway, work is continuing amongst a number of areas here at St James Park as part of the redevelopment project.

As always, full checks are put in place to ensure that the stadium is ready for matchdays.

Here is an update on the activities over the last week:

IP Office Main Stand

A new sewerage tank is being installed for the new changing rooms under the IP Office Main Stand.

Work continues in the changing room area

Away End

 

The installation continues of the railings on the lowered wall of the away end.

New first aid and control facilities were delivered to their temporary location last week.

 

The new cabins in their temporary location.

A look at the progress inside the new first aid facilities in the cabin.

Thatchers' Big Bank

 

The new ladies toilets for the Big Bank have taken shape.

The personalised bricks have been reinstated in Stadium Way.